In the event of a disaster, you might need to start an individual recovery node, a group of recovery nodes, or all the recovery nodes on the DR Appliance.
• You can change the memory allocation of PNs so that the total is less than the memory on the onQ Appliance.
•
1. (Optional) Consider suspending RN tests to “free up” resources.
3.
4.
5.
6. Click Apply to start all the DR recovery nodes.When you start in production mode, the startup order will take into account the order you specified in Configure startup dependencies.
1.
2.
3.
4.
1. (Optional) Consider suspending RN tests to “free up” resources.
3.
4. Locate the Power State column.When you click the button in the Power State column, a box appears that offers you a choice between the following two alternatives: Power On: Test Network or Power On: Production Network.
5. Choose the Power On: Production Network power option.
|
| v3.8 HF1 |